Office of Broadband Development Update Sep 9 2026: Upcoming Task Force meeting, digital opportunity, BEAD and Line Extension updates

From the MN Office of Broadband Development…

Broadband Matters: Office of Broadband Development Updates

  • Broadband Task Force, September meeting plans
  • Digital Opportunity updates
  • Broadband, Equity, Access and Deployment (BEAD) updates
  • Line Extension Connection Program, registration open for residents and businesses

Broadband Task Force, September meeting plans

The Broadband Task Force will meet Wednesday September 16 at 10 a.m. CT. This meeting will be held virtually and is open to anyone from the public to attend. Information on this upcoming meeting, including the Teams link to join, as well as past meetings can be found on the Broadband Task Force webpage.

Digital Opportunity updates

The Federal Communications Commission (FCC) is to review the E-Rate Program, information from the FCC available on the Federal Register. Additional resources include:

Additionally, on the federal news of the reinstatement of the Digital Equity Competitive Grant Program, Benton Institute recently published The Tight Clock for Reopening the Digital Equity Competitive Grant Program. At this time, our office has not received updated guidance from NTIA regarding whether state’s Digital Equity Capacity funds or related grants may be reinstated.

As OBD continues to navigate ongoing developments please feel free to reach out to our office with questions at DEED.broadband@state.mn.us or by phone at 651-259-7610.

Broadband, Equity, Access and Deployment (BEAD) updates

OBD is continuing to work through required project scope changes and preparing contracts for execution. Updated information and resources can be found on the OBD BEAD webpage. The NTIA must approve project scope changes and has informed OBD the review process can take several weeks. The current federal contracting deadline is October 8, 2026.

On September 3, 2026, the NTIA announced a new BEAD Supplemental Deployment Policy Notice that introduces an updated process for BEAD implementation. States are actively reviewing this new guidance to better understand its implications. As NTIA releases additional information, including details on timelines, states will provide further updates and resources to keep partners and providers informed.

BEAD mentions in the news include:

Providers and community members can contact OBD at DEED.broadband@state.mn.us with questions.

Line Extension Connection Program, registration open for residents and businesses

Registration remains open for residents and businesses for future rounds of the Line Extension Connection Program.

For assistance completing the application, or to request a paper form to complete, please call 651-259-7610 or email DEED.broadband@state.mn.us.

More information and registration are available on the Line Extension Connection Program webpage.

Office of Broadband Development Update July 29 2026: East Central Energy (ECE)

From the Office of Broadband Development…

Broadband Matters: Office of Broadband Development Updates

  • Broadband, Equity, Access and Deployment (BEAD) updates
  • Upcoming Tribal broadband summit + federal funding opportunities
  • Digital opportunity, community update
  • Line Extension Connection Program, registration open for residents and businesses

Broadband, Equity, Access and Deployment (BEAD) updates

Minnesota is excited to announce its very first fiber project for BEAD has an executed contract and approved National Environmental Protection Act (NEPA) decision memo. This East Central Energy (ECE) Fiber project in East Central Minnesota is expected to serve 3,750 locations:

Bringing broadband to unserved and underserved communities takes true partnership. We extend our sincere thanks to the Minnesota Office of Broadband Development and DEED for their collaborative approach, responsiveness, and shared commitment to connecting rural Minnesota. Their assistance in helping us finalize and execute our BEAD application was invaluable.” Ty Houglum, Vice President/Chief Information Officer, ECE 

Minnesota BEAD Map with ECE Central Minnesota project.

OBD is continuing to work through required project scope changes and preparing contracts for execution. These scope changes often include removing locations newly identified as already served or re‑awarding locations when providers decline an award. Updated information and resources can be found on the OBD BEAD webpage.

Because the National Telecommunications and Information Administration (NTIA) must approve these project scope changes, the review process can take several weeks. OBD will continue coordinating closely with partners to keep projects moving and to meet the federal contracting deadline of October 8, 2026.

Providers and community members can contact OBD (DEED.broadband@state.mn.us) with questions.

Upcoming Tribal broadband summit + federal funding opportunities

Early bird registration is open for the 2026 NTTA Tribal Broadband Regional Southern Plains Summit, September 21-23 at the Hard Rock Hotel & Casino in Tulsa, Oklahoma. The summit will look to advance broadband connectivity and digital sovereignty throughout Indian Country and cover topics like data sovereignty, AI & emerging technology, broadband equity & infrastructure, and cultural continuity. More information and registration is available online.

Additionally, NTIA Announced Two New Funding Opportunities to Expand Broadband Connectivity on Tribal Lands. Applications are due September 17, 2026. More information is available on NTIA’s BroadbandUSA webpage including:

Digital opportunity, community update

OBD is actively monitoring developments given the recent federal court ruling impacting the Digital Equity Competitive Grant Program. At this time, our office has not received updated guidance from NTIA regarding whether Digital Equity funds or related grants may be reinstated.

We understand how important this is to Minnesota. As new information becomes available, OBD will relay updates through this newsletter and on the OBD Digital Opportunity webpage.

As we navigate these ongoing developments together, please feel free to reach out to our office with questions at DEED.broadband@state.mn.us or by phone at 651-259-7610.

Line Extension Connection Program, registration open for residents and businesses

Registration remains open for residents and businesses for future rounds of the Line Extension Connection Program.

For assistance completing the application or to request a paper form to complete, please call 651-259-7610 or email DEED.broadband@state.mn.us.

More information and registration are available on the Line Extension Connection Program webpage.