The St. Louis County Board on Tuesday approved an agreement with the city of Hermantown regarding road work near the proposed Google data center.
The Hermantown City Council recently approved a development agreement for the data center. The facility would be built near Morris Thomas Road and Midway Road.
St. Louis County public works officials say road improvements are needed to handle traffic from construction and operation of the data center.
Tuesday’s agreement requires the developer, a subsidiary of Google, to pay for that work. The work includes road reconstruction, turn lanes and traffic signals. County leaders say the road construction project would cost between $4 million and $6 million.
Jim Foldesi, the county’s deputy county administrator for public works and transportation, said the agreement protects county infrastructure.