The board approved amendments to Arvig Elk River and Haven/Clear Lake Broadband Grant Program agreements
Arvig received ARPA Broadband Access Program grants for several projects in 2023. The Elk River Round #1, Elk River Round #2, and the Clear Lake/Haven Round #2 projects were completed (or are very near to completion) under budget.
Staff recommended utilizing the remaining funds ($453,300) to expand the original scope of each project. The revised project scope would serve an additional 71 passings, which include 10 unserved and 61 underserved properties in Elk River, Haven, and Clear Lake.