OBD Weekly Office Hours, March 11: New office hours added

A couple dozen people still show up for the weekly Office of Broadband Development Office Hours where they review what’s happening with BEAD and answer questions. The one-hour meeting is often much shorter than an hour but it’s a good time if/when you do have questions.

Highlights from presentation:

  • Pre-qualification applications are coming in
  • Sub Round 11A opens March 24 – fiber and priority projects. You can propose your own location areas
  • Two new office hours added

From Chat:

Questions:

What about federal changes to BEAD?
We are proceeding under guidance we currently have. But we stayed tuned for changes.

The list posted on 3/3, there are about 10,000 addresses with an asterisk. Is this the final final list?
No there will continue to be changes. If we may see address dropping of the list. But 10,000 seems a lot. Lots of folks said their ACAM projects were going to be getting fiber so that removed a lot of addresses.